REO
Brodarevo 2
Brodarevo 2 (25MW capacity) covers the River Lim down-river of the town of Brodarevo, to the Bosnian (Serbian Republic) border. The River Lim is a tributary of the River Drina, one of the major waterways of the region, which is sparsely populated, with most of the surface rights along the River Lim owned by the state.



Click to Play Video


Hydro Power Plant Name: Brodarevo 2 (downstream)
Municipality: Prijepolje
Basin: Drina
Main river flow: Lim
Geographical Location: 10 km downstream from Brodarevo
Gross head: 21 m
Length of the required dam (at the top): 250 m
Dam height: 23 m
Level of regular backwater curve: 486 m.a.s.l.
Level of spillway top: 486 m.a.s.l.
Maximum reservoir volume: 16 000 000 m3
Effective volume: 5 500 000 m3
Reservoir length: 9.5 km
A length of required road infrastructure: 9 km
Closest point of the transmission grid: DV 1118 - TS Prijepolje, 5 km
Length of a connection power line
    1. for the purpose of generating electricity delivery:
    2. for the purpose of auxiliary supply of Hydro Power Plant:

500 m
500 m
Turbines number: 3
Operating turbine range: 30 - 100%
Installed discharge: 150 m3/s (30 + 2 x 60)
Installed power: 25 MW
Annual electricity generation: 96 800 MWh
 