REO
Brodavero 1
Brodarevo 1 (23MW capacity) covers the River Lim upstream of Brodarevo to the Montenegro border. The River Lim is a tributary of the River Drina, one of the major waterways of the region, which is sparsely populated, with most of the surface rights along the River Lim owned by the state.


Click to Play Video


Hydro Power Plant Name:

Brodarevo 1 (upstream)

Municipality:

Prijepolje

Basin:

Drina

Main river flow:

Lim

Geographical Location:

3 km upstream from Brodarevo

Gross head:

20 m

Length of the required dam (at the top):

70 m

Dam height:

22 m

Level of regular backwater curve:

518 m.a.s.l.

Level of spillway top:

518 m.a.s.l.

Maximum reservoir volume:

7 800 000 m3

Effective volume:

1 500 000 m3

Reservoir length:

7.5 km

A length of required road infrastructure:

7 km

Closest point of the transmission grid:

DV 1118 -- EVP Brodarevo, 7 km

Length of a connection power line
    1. for the purpose of generating electricity delivery:
    2. for the purpose of auxiliary supply of Hydro Power Plant:

7 km
2.3 km

Turbines number:

3

Operating turbine range:

30 -- 100%

Installed discharge:

143 m3/s (23 + 2 x 60)

Installed power:

23 MW

Annual electricity generation:

87 960 MWh

 